Client:
National Center “Junior Academy of Sciences of Ukraine”
Problem:
The client set the following tasks:
- to provide the facility with a backup power source
- to supply a diesel generator of the appropriate capacity
- to install the equipment at the site
- to perform a full commissioning
- to ensure timely completion under high-risk conditions
What equipment was installed:
The following was installed as part of the project:
- Diesel generator: Smart Grid DG-E150
The scope of work included:
- equipment delivery
- on-site installation
- commissioning
What were the challenges involved in implementing the project:
- Project implementation amid wartime conditions and external risks
- The need for rapid delivery and commissioning
- High standards for installation quality and system reliability
- Coordination of work at an operational facility
Result:
- A project developed and approved by government agencies
- A reliable backup power source to ensure uninterrupted operation of the facility
- A fully executed turnkey project
- On-time delivery and no complaints
- High-quality installation and stable equipment operation
- Proof of the contractor’s reliability even under challenging conditions